在设计和工程施工过程中,以及其后雇主认为为了完成承包商的义务所需要的期间内,承包商应对工作的规划、安排、指导、管理、检验和试验,提供一切必要的监督.
此类监督应由足够的人员执行,他们应具有交流所有语言(第1.4款[法律和语言]所规定的) 、以及合乎要求地、安全地实施工程各项作业所需的足够的知识(包括需要的方法和技术、可能遇到的危险和预防事故的方法).
Throughout the design and execution of the Works, and as long thereafter as is necessary to fulfill the contractor’s obligations, the Contractor shall provide all necessary superintendence to plan, arrange, direct, manage, inspect and test the work.
Superintendence shall be given by a sufficient number of persons having adequate knowledge of the language for communications (defined in Sub-Clause 1.4[Laws and Language]) and of the operations to be carried out (including the methods and techniques required, the hazards likely to be encountered and methods of preventing accidents), for the satisfactory and safe execution of the Works.