当基准日期后,工程所在国的法律有改变(包括施用新的法律,废除或修改现有法律),或对此类法律的司法或政府解释有改变,对承包商履行合同规定的义务产生影响时,合同价格应考虑由上述改变造成的任何费用增减,进行调整.
如果由于这些基准日期后做出的法律或此类解释的改变,使承包商已(或将)遭受延误和(或)已(或将)招致增加费用,承包商应向雇主发出通知,并应有权根据第20.1款[承包商的索赔]的规定提出:
(a) 根据第8.4款[竣工时间的延长]的规定,如果竣工已(或)将受到延误,对任何此类延误给予延长期;
(b) 任何此类费用应加入合同价格,给予支付.
雇主收到此类通知后,应按照第3.5款[确定]的要求,对这些事项进行商定或确定.
The Contract Price shall be adjusted to take account of any increase or decrease in Cost resulting from a change in the Laws of the Country (including the introduction of new Laws and the repeal or modification of existing Laws) or in the judicial or official governmental interpretation of such Laws, made after the Base Date, which affect the Contractor in the performance of obligations under the Contract.
If the Contractor suffers (or will suffer)delay and/or incurs (or will incur) additional Cost as a result of these changes in the Laws or in such interpretations, made after the Base Date, the Contractor shall give notice to the Employer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost, which shall be added to the Contract Price.
After receiving this notice, he Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.